Update Construction Progress Of Suncasa Project On September 16, 2020

13/10/2020 03:52

Construction progress:

– Fabricate floor beam, ground beam

– Installing formwork for stairs D-31.27,28

– Installing steel for floor beam D-31.36,37,38

– Moving land, crush land for foundation  

– Compacting land for ground beam D-31.49,50, Compacting land for ground floor D-31.42,43,44,45

– Installing cos+3550 floor for house 36,37,38

– Compacting soil for ground floor of house 42,43,44

– Installing formwork for stairs of house 27,28

Pictures of contruction

Update Construction Progress Of Suncasa Project On September 16, 2020
Update Construction Progress Of Suncasa Project On September 16, 2020
Update Construction Progress Of Suncasa Project On September 16, 2020


Related news


Groundbreaking Ceremony of Project 08 – BW Thoi Hoa Industrial Development Company Limited

In the joyful atmosphere of welcoming the new year 2021, on the morning of December 29, 2020, BW Industrial Development […]

Show more
The BW VSIP IIA project achieved 50,000 hours of safe working

In addition to performing well safety tasks at all projects, Golden Lotus Construction also regularly updates and innovates construction technologies, […]

Show more
Project progress of BW Tan Uyen 12/2020

PROJECT: PROJECT 10 – INDUSTRIAL DEVELOPMENT AND HAU CAN BW TAN UYEN COMPANY LIMITED LOCATION: No. 2, Vsip II-A, Street 10, VN-Singapore […]

Show more