Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020

12/10/2020 08:23

RESEARCH AND DEVELOPMENT

– Fabricating and installing septic tank, axis 1-2
– Fabricating and installing stairs, axis 8-9, 4th floors to roof.
– Paving 2nd floor, tiling 3rd floor, 4th floor.
– Exterior plastering of wall for C / 3-4.9-10 axis. Putty outside.
– Installation of door frame on 2nd floor, Roof waterproofing.


2. COMPLETED FACTORY
– Fabrication and installation of steel for floor beam 2.9, 1-2 axis / D-H
– Plastering ceiling on 2nd floor, outer surface of M-J axis.
– Building walls, the 3rd floor, H axis / 9-17, plastering the third floor outside, the A-H / 16 axis.
– Grinding ceilings and plastering pillars on the 3rd floor.
– Roof waterproofing.
– Installation of steel for floor, axis 2-9 / M-L, axis 2-9 / K-J.
– Prepare to pour concrete for wall phase 2 axis 9a-16 / K-J.

3. DYEING FACTORY
– Chống thấm mái thi công màng kho.
– Construction of wall, the 3rd floor, room AC.
– Continue to grind ceiling columns, plaster on the 1st and 2nd floor, 3rd floor.
– Fabrication and installation of floor beam cote 6.1, girder bridge No. 3.
– Dismantle stair axis 11-12 from cote 6.2-14.6.
– Roof waterproofing, construction of warehouse membranes.


4. INFRASTRUCTURE

– Construction of temporary drainage, temporary roads.
– Construction of ditch A10-A11, A11-A18, A09-A10.
– Construction of wastewater from NT3-01 to NT3-05 section.
– Compacting CP for streets DA5, D2.4.

5. FIRE PROTECTION TANK, COAL WAREHOUSE
– Fabrication and installation of formwork for pump room
– Fabrication and installation of formwork for ground beam of the warehouse.
– Clean the fire protection tank.

6. WASTE WATER TANK S08A
– Installation of reinforcement, formwork for wall of ditch cos +4000.


7. ME SYSTEM

– Construction of water supply to WC, Chiseling, putting pipe for dyeing factory, completed factory, R&D house
– Construction of fire extinguishing system for R&D house, dyeing workshop, completed factory.
– Construction of WC water supply and drainage pipes to completed factory.


Pictures of construction of Mahang:

Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020
Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020
Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020
Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020


Related news


Groundbreaking Ceremony of Project 08 – BW Thoi Hoa Industrial Development Company Limited

In the joyful atmosphere of welcoming the new year 2021, on the morning of December 29, 2020, BW Industrial Development […]

Show more
The BW VSIP IIA project achieved 50,000 hours of safe working

In addition to performing well safety tasks at all projects, Golden Lotus Construction also regularly updates and innovates construction technologies, […]

Show more
Project progress of BW Tan Uyen 12/2020

PROJECT: PROJECT 10 – INDUSTRIAL DEVELOPMENT AND HAU CAN BW TAN UYEN COMPANY LIMITED LOCATION: No. 2, Vsip II-A, Street 10, VN-Singapore […]

Show more