Construction News



Update Construction Progress Of Xindadong Textiles – Dung Quat On Sep 17, 2019

Construction works:
TEXTILE FACTORY
– Aligning the beam formwork, mounting beam steel + 9.9m axis 12-14 / H-G
– Building and plastering axis 12-21 / G-H, 23 / E-H; 12-21 / A-B; 22-23 / A-D
– Fabrication of floor reinforcement 1m
– Concrete grinding for floor beam, axis 22-23 / A-E

Show more

Groundbreaking Ceremony Of Tating Plastic Factory – Phase 2

On August 2019, Golden Lotus Joint Stock Company cooperated with Tating Plastic Co.,

Show more

Update Construction Progress Of BW Project – Phase 3 On Sep 17, 2019

1. Factory C11-C12: Installation of steel structure column (100%)
2. Factory C11-C12: Installation of collar beam with steel structure

Show more

Update Construction Progress Of Mahang Project – Dung Quat On Oct 28, 2019

Construction of reinforcement, formwork columns, beams, dyeing workshop floors,

Show more

Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Sep 22, 2019

Works has been done:
TEXTILE FACTORY
– Fabrication and installation of formwork, reinforcement for electric floor 1m
– Building and plastering 1st ,2nd floor, axis 12-21 / G-H; 12-17 / A-E; 22-23 / A-D
– Concrete grinding for floor beam, axis 22-23 / A-E

Show more

Updated progress of Mahang – Dung Quat project on September 27, 2019

Contents of construction work:
Installing reinforcement, formwork for column of wall

Show more