Update Construction Progress Of Best Pacific Project – Phase 2 On February 17, 2019
Year of the Pig – Chinese New Year is over, continuing with construction work to complete on schedule. Here is an update on construction progress of Best Pacific Vietnam Phase 2
Works have done
- Installing fireproof wall frame for 3rd floor, N axis and pillar 20A;
- Fabricating, covering asbestos sheathing for wind pipe of 2nd, 3rd floor
- Connection of wind pipe of 2nd floor
- Installing light trough for 2nd floor
Pictures of construction: