Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On February 28, 2019

  1. CONSTRUCTION OF HOUSE
  1. Clearing the base of the 1st floor, axis (1-5) / (A-N);
  2. Fabricating formwork for foundation of ditch;
  3. Dado wall of wet room for 1st floor;
  4. Complete the three levels around the house;
  5. Construction of wall, N axis / (3-5);
  6. Lighting: screwing box and dragging control of 2nd floor, hanging lights of 3rd floor (15-16) / (C-K) axis;
  7. Air-conditioning – wind pipe: fabrication, connecting wind pipes for 2nd, 3rd floors
  8. Chiller: Hanging chiller pipe for the 2nd floor, axis 5 / (A-N). Construction of chiller machine room, the 1st floor (13-15) / A Axis;
  9. Cable tray: Installing cable tray, 1st floor, axis (5-16) / (D-G);
  10. Water supply and drainage: build a manhole outside the axis 20;
  11. Putty, putty removing for wall of the first floor, N axis;
  12. Screwing fireproof wall of stairs, 20A and 17N axis

Pictures of construction:

Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On February 28, 2019
Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On February 28, 2019
Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On February 28, 2019
Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On February 28, 2019