Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On March 28, 2019

CONSTRUCTION OF HOUSE

  1. Construction and plastering of walls, axis N and axis 1
  2. Lighting: installation of 1st floor lights, installing power of socket for 2nd floor. Hanging V lights for the 3rd floor;
  3. Air-conditioner, wind duct: Construction of wind duct at 1st ,2st floor
  4. Cable troughs: installation of cable troughs at 2nd, 3rd floors;
  5. Install chiller pipe on cooling tower. Connecting chiller pipe on 3rd floor;
  6. Drill the pipe rack on the piperack
  7. Fire protection: Installation of smoke detector for 2nd floor. Installation of fire fight water hose for 2nd floor.
  8. Plastering fireproof wall, 3rd floor, plastering wall, N axis;
  9. Crewing fireproof wall in the area of stairs (A-B) axis / (7-8)
  10. Weld reinforced beam to hang piperack (M-N) axis / (7-8) and (B-C) / (14-18);
  11. Installing piperack (1-2) / (A-B);
  12. Fabricating pipe rack in house
  13. Fabricating and installing piperack around D2;
  14. Plastering wall, 3rd floor;
  15. Screwing plastered wall, 3rd floor;

Pictures of construction

Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On March 28, 2019
Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On March 28, 2019
Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On March 28, 2019
Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On March 28, 2019