Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On March 28, 2019
CONSTRUCTION OF HOUSE
- Construction and plastering of walls, axis N and axis 1
- Lighting: installation of 1st floor lights, installing power of socket for 2nd floor. Hanging V lights for the 3rd floor;
- Air-conditioner, wind duct: Construction of wind duct at 1st ,2st floor
- Cable troughs: installation of cable troughs at 2nd, 3rd floors;
- Install chiller pipe on cooling tower. Connecting chiller pipe on 3rd floor;
- Drill the pipe rack on the piperack
- Fire protection: Installation of smoke detector for 2nd floor. Installation of fire fight water hose for 2nd floor.
- Plastering fireproof wall, 3rd floor, plastering wall, N axis;
- Crewing fireproof wall in the area of stairs (A-B) axis / (7-8)
- Weld reinforced beam to hang piperack (M-N) axis / (7-8) and (B-C) / (14-18);
- Installing piperack (1-2) / (A-B);
- Fabricating pipe rack in house
- Fabricating and installing piperack around D2;
- Plastering wall, 3rd floor;
- Screwing plastered wall, 3rd floor;