Update Construction Progress Of BW Project – Phase 3 On Sep 17, 2019

Construction works have done:

Factory C11-C12

1. Factory C11-C12: Installation of steel structure column (100%)
2. Factory C11-C12: Installation of collar beam with steel structure (100%)
3. Factory C11-C12: Installation of reinforcement for column of 2nd floor of the office area (100%)
4. Factory C11-C12: Installation of wind ridge beam with steel structure
5. Factory C11-C12: Building the wall of Q axis, factory area
6. Factory C11-C12: Installation of board lining, wall-bracing reinforcement, lintel

Factory B11

1. Factory B11: Pouring concrete for column of 2nd floor of office area (50%)
2. Factory B11: Installation of board lining, reinforcement for column of 2nd floor of the office area (80%)
3. Factory B11: Installation of collar beam with steel structure
4. Factory B11: Plastering wall, axis 13 (40%)
5. Factory B11: Installation of board lining, reinforcement for wall-bracing, lintel

Factory B12

1. Factory B12: Pouring concrete for column of 2nd floor of office area (50%)
2. Factory B12: Installation of board lining, reinforcement for column of 2nd floor of the office area (80%)
3. Factory B12: Installation of board lining, reinforcement for wall bracing, lintel

Factory C4

1. Factory C4: Pouring concrete for floor of 2nd floor of the office area (50%)
2. Factory C4: Installation of board lining, reinforcement of floor of 2nd floor of the office area (85%)
3. Factory C4: Rolling corrugated iron for roof
4. Factory C4: Installation of board lining, reinforcement for wall bracing, 
lintel, axis 13 factory area

Factory C5

1. Factory C5: Installing scaffolding on floor of the 2nd floor of the office area
2. Factory C5: Installing
 collar beam with steel structure (25%)
3. Factory C5: Installation of board lining, wall-bracing reinforcement, 
lintel

Factory C6

1. Factory C6: Installing scaffolding on floor of the 2nd floor of office area – Installation of board lining of floor for 2nd floor, office area
2. Factory C6: Installation of steel structure columns
3. Factory C6: Building wall, axis 1 of factory area

Infrastructure

1. Infrastructure: Installation of culverts and holes of factory C5, B12

Fire protection

1. Fire protection: Fabricating pipe DN200
2. Fire protection: Construction of infrastructure pipeline DN200

MEP

1. MEP: Construction of infrastructure drainage of factory C11
2. MEP: Construction of HDPE pipes
3. MEP: Construction and installation of water drainage and waiting electrical pipes for the 2nd  floor, office area of factory C4

Pictures of construction:

Update Construction Progress Of BW Project – Phase 3 On Sep 17, 2019
Update Construction Progress Of BW Project – Phase 3 On Sep 17, 2019
Update Construction Progress Of BW Project – Phase 3 On Sep 17, 2019
Update Construction Progress Of BW Project – Phase 3 On Sep 17, 2019

GOLDEN LOTUS CONSTRUCTION JSC .,