Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019

Content of works has done:

Factory C11-C12

  1. Factory C11-C12: Mounting columns, collar beam, ridge beam (100%)
  2. Factory C11-C12: Pouring concrete for column, the second floor of office area (100%)
  3. Factory C11-C12: Completing of column, collar beam, ridge beam (100%)

    4. Factory C11-C12: Remove scaffolding, board lining of floor, factory C12

Factory B11

  1. Factory B11: Pouring concrete for floor of 2nd floor of office area (100%)
  2. Factory B11: Installation of board lining, reinforcement loor of 2nd floor of office area (100%)
  3. Factory B11: Completed columns, collar beam, ridge beam (100%)

     4. Factory B11: Pouring concrete to wall bracing and linens in the factory area (70%)

Factory B12

  1. Factory B12: Pouring concrete for floor of 2nd floor of the office area (100%)
  2. Factory B12: Installation of board lining, reinforcement for floor of 2nd floor of the office area (100%)

     3. Factory B12: Pouring concrete to wall bracing and linens in the factory area (85%)

Infrastructure

1.Infrastructure: Excavation of soil, installation of culverts and manholes of factories B11, B12

Pictures of construction

Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019
Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019
Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019
Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019

GOLDEN LOTUS CONSTRUCTION JSC .,