Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019
Content of works has done:
Factory C11-C12
- Factory C11-C12: Mounting columns, collar beam, ridge beam (100%)
- Factory C11-C12: Pouring concrete for column, the second floor of office area (100%)
- Factory C11-C12: Completing of column, collar beam, ridge beam (100%)
4. Factory C11-C12: Remove scaffolding, board lining of floor, factory C12
Factory B11
- Factory B11: Pouring concrete for floor of 2nd floor of office area (100%)
- Factory B11: Installation of board lining, reinforcement loor of 2nd floor of office area (100%)
- Factory B11: Completed columns, collar beam, ridge beam (100%)
4. Factory B11: Pouring concrete to wall bracing and linens in the factory area (70%)
Factory B12
- Factory B12: Pouring concrete for floor of 2nd floor of the office area (100%)
- Factory B12: Installation of board lining, reinforcement for floor of 2nd floor of the office area (100%)
3. Factory B12: Pouring concrete to wall bracing and linens in the factory area (85%)
Infrastructure
1.Infrastructure: Excavation of soil, installation of culverts and manholes of factories B11, B12