Update Construction Progress Of Mahang Project – Dung Quat On September 08, 2019
Works have done
- Construction of temporary office
- Construction of foundation excavation, pouring lining, reinforcement, formwork, pouring concrete for foundation of dyeing factory, completed factory, and wastewater treatment tank
Pictures of construction



