Update Construction Progress Of Mahang Project – Dung Quat On September 18, 2019

Contents of main works have done:

Construction of temporary offices;

Construction of foundation excavation, pouring lining, reinforcement, formwork, pouring concrete for foundation of dyeing workshop, completed workshop, waste water treatment tanks.

Illustrating pictures of construction