Update Construction Progress Of Mahang Project On Aug 04, 2020

  1.  COMPLETED FACTORY
    –  Installing ditch, steel for machine base of axis 14
    –  Installing defect for floor of 2nd floor
    –  Installing defect, plastering for room
    –  Installing air ventilation fan.
  2. DYEING FACTORY
    –  Maintenance and cutting of concrete sealing joints for foundation of A-B axis / 3-10.
    –  Installing grinding, defect in room
    –  Welding steel V for ditch of K axis.
    –  Installing fireproof doors on floors.
  3.  INFRASTRUCTURE
    –  Implementing cement concrete maintenance of street section 3.1
  4. FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE
    –  Installing foundation formwork of machine for boiler house
  5.  ME System
    –  Installing 2.9m floor drainage pipe of completed factory.
    –  Installing fire fighting on the first floor of dyeing factory.
    –  Installing fire alarm for chemical warehouse.

Pictures of construction

Update Construction Progress Of Mahang Project On Aug 04, 2020
Update Construction Progress Of Mahang Project On Aug 04, 2020
Update Construction Progress Of Mahang Project On Aug 04, 2020
Update Construction Progress Of Mahang Project On Aug 04, 2020