Update Construction Progress Of Mahang Project On Aug 04, 2020
- COMPLETED FACTORY
– Installing ditch, steel for machine base of axis 14
– Installing defect for floor of 2nd floor
– Installing defect, plastering for room
– Installing air ventilation fan. - DYEING FACTORY
– Maintenance and cutting of concrete sealing joints for foundation of A-B axis / 3-10.
– Installing grinding, defect in room
– Welding steel V for ditch of K axis.
– Installing fireproof doors on floors. - INFRASTRUCTURE
– Implementing cement concrete maintenance of street section 3.1 - FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE
– Installing foundation formwork of machine for boiler house - ME System
– Installing 2.9m floor drainage pipe of completed factory.
– Installing fire fighting on the first floor of dyeing factory.
– Installing fire alarm for chemical warehouse.