Update Construction Progress Of Perennial Cable Project – Phase 3 On May 18, 2020

Update Construction Progress Of Perennial Cable Project – Phase 3 On May 18, 2020

Construction progress of Perennial Cable Project – Phase 3

– Fabrication of formwork for beam bottom, iron and steel, column of roof X1-8 / Y1-5 axis, factory E

– Concrete grinding for floor beam, 2nd floor X1-8 / Y1-5 axis, factory E

– Transporting scrap boards to 3rd floor of Factory E

–  Installing reinforcement for column of  2nd floor, office area of factory

–  Building auxiliary wall

–  Combine formwork into ditch, ditch route A21-A22

–  Installing reinforcement for ditch route A4 – A4-1 

–  Pour concrete for bottom of ditch, ditch route A4 – A4-1

Pictures of construction

Update Construction Progress Of Perennial Cable Project – Phase 3 On May 18, 2020
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 18, 2020
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 18, 2020
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 18, 2020