Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On February 28, 2019
Update Perennial Cable Vietnam Project on February 28, 2019
Factory B
– Patching and sealing for hole of scaffolding, covering X1, Y5, axis, factory B
– Remove the scaffolding outside, X8 axis, factory B
– Remove power for 2nd outside of factory, X4-X6 / Y1 axis, factory B
– Rolling water painting 1, 2 outside of parapet wall of factory B
– Putty 2 sides in attic; patch outside, X1, Y5 axis, factory B
– Installing and screwing silicon louver for the first floor of factory B
– Construction of compressed air for the second floor of factory B
– Installing fire fighting box, factory B
Factory C
– Patching outside, 3rd floor, Y5 axis, factory C
– Construction of compressed air system, 3rd floor, factory
– Construction of water pipes, factory C
– Construction of cable tray, 3rd floor, factory C