Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On February 28, 2019

Update Perennial Cable Vietnam Project on February 28, 2019

Factory B

– Patching and sealing for hole of scaffolding, covering X1, Y5, axis, factory B

– Remove the scaffolding outside, X8 axis, factory B

– Remove power for 2nd outside of factory, X4-X6 / Y1 axis, factory B

– Rolling water painting 1, 2 outside of parapet wall of factory B

– Putty 2 sides in attic; patch outside, X1, Y5 axis, factory B

– Installing and screwing silicon louver for the first floor of factory B

– Construction of compressed air for the second floor of factory B

– Installing fire fighting box, factory B


Factory C

– Patching outside, 3rd floor, Y5 axis, factory C

– Construction of compressed air system, 3rd floor, factory

– Construction of water pipes, factory C

– Construction of cable tray, 3rd floor, factory C

Pictures of construction:

Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On February 28, 2019
Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On February 28, 2019
Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On February 28, 2019
Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On February 28, 2019