Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On March 14, 2019
Update construction status of Perennial Cable Vietnam Project – Phase 2 on March 14, 2019
Contents of main construction works:
Factory B
– Installation of waste water drainage pipe, Y5 axis, factory B
– Painting 2nd time for stairs, X7-X8 axis, 1st floor, factory B
– Priming Paint outside, X6-X8 / Y1 axis, workshop B
– Construction of lighting equipment for the 3rd floor of factory B
– Construction of lighting equipment for the 3rd floor of factory B
Factory C
– Repair of cracks for 3rd floor of factory C
– Digging wastewater drainage pipe of Y5 axis, factory C
– Fabrication and installation of reinforcement, formwork, pouring concrete into rainwater drainage ditch, Y1 axis, factory C
– Cleaning glass doors, factory C