Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On March 14, 2019

Update construction status of Perennial Cable Vietnam Project – Phase 2 on March 14, 2019

Contents of main construction works:

Factory B

– Installation of waste water drainage pipe, Y5 axis, factory B

– Painting 2nd time for stairs, X7-X8 axis, 1st floor, factory B

– Priming Paint outside, X6-X8 / Y1 axis, workshop B

– Construction of lighting equipment for the 3rd floor of factory B

– Construction of lighting equipment for the 3rd floor of factory B

Factory C

– Repair of cracks for 3rd floor of factory C

– Digging wastewater drainage pipe of Y5 axis, factory C

– Fabrication and installation of reinforcement, formwork, pouring concrete into rainwater drainage ditch, Y1 axis, factory C

– Cleaning glass doors, factory C

Pictures of construction:

Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On March 14, 2019
Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On March 14, 2019
Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On March 14, 2019
Update Construction Progress Of Perennial Cable Vietnam Project – Phase 2 On March 14, 2019