Update Construction Progress Of Tating Plastic Project On Dec 23, 2018

After 1 month of construction, Tating Plastic project is being constructed by Bong Sen Vang as scheduled

Factory 1,2

  1. Installation of reinforcement, formwork for foundation, ground beam;
  2. Backfilling, leveling soil for ground;

Warehouse

  1. Excavation foundation, cutting pile head
  2. Installation of reinforcement, formwork, pouring concrete for foundation;
  3. Installation of  reinforcement, formwork for ground beam.

Training house

  1. Excavation foundation;
  2. Cutting pile head;
  3. Installation of reinforcement, pouring concrete for foundation;

* Canteen building

  1. Excavation foundation;
  2. Cutting pile head;
  3. Installation of reinforcement, formwork, pouring concrete for foundation;

* Office

  1. Levelling ground

*Infrastructure

  1. Installation of storm, water drainage manhole;
  2. Levelling ground of road;
  3. Instalation of V steel for manhole;
  4. Modify road ground as chance master plan.

Fence

  1. Plastering for column;
  2. Fabrication, installation steel fence

Water tank

  1. Excavation for foundation;
  2. Driving bamboo piles.

Real Construction Pictures:

Update Construction Progress Of Tating Plastic Project On Dec 23, 2018
Update Construction Progress Of Tating Plastic Project On Dec 23, 2018
Update Construction Progress Of Tating Plastic Project On Dec 23, 2018