Update Construction Progress Of Vietnam Best Pacific Project – Phase 2 On Jan 28, 2019

Update construction status of Vietnam Best Pacific Project – Phase 2 near Lunar New Year Jan 28, 2019

  1. Covering asbestos sheathing, Installing wind pipe of 2nd floor, 3rd floor;
  2. Installing chiller pipe, 9 axis, level 3
  3. Remove scaffolding N axis / (13-20);
  4. Installing doors at locations to remove scaffolding;
  5. Installing fireproof wall of floor 3; 20N axis

Pictures of construction: