Update Construction Progress Of Vietnam Best Pacific Project – Phase 2 On Jan 28, 2019
Update construction status of Vietnam Best Pacific Project – Phase 2 near Lunar New Year Jan 28, 2019
- Covering asbestos sheathing, Installing wind pipe of 2nd floor, 3rd floor;
- Installing chiller pipe, 9 axis, level 3
- Remove scaffolding N axis / (13-20);
- Installing doors at locations to remove scaffolding;
- Installing fireproof wall of floor 3; 20N axis