– Building and plastering wall foot A-B axis;
– Grinding and patching the wind ditch surface;
– Construction of ramp axis 23;
– Tiling brick for toilets
– Painting color for axis 12 axis, complete air conditioning room No. 4
– Construction of plaster ceiling axis 16-17 / B-D
– Construction of the frame of the anti-flow wall
– Cleaning the roof, membrane waterproofing axis 19-23 / D-H


PREPARATION FACTORY FOR RAW MATERIAL
– Building and plastering deck floor, axis C-G / 20
– Paving the toilet on the first floor of the office area
– Paint to complete the second floor of the office area
– Construction of walls, plastering wall of basement axis K-M / 5-11;
– Putty, rolling axis K / 20-25; deck floor 5.4m; axis C / 16-20
– Installation of frames, plaster ceiling; screwing plaster wall; screwing toilet’s ceiling

WASTEWATER TREATMENT AREA
– Plastering wall outside the operation house
– installation of formwork and reinforcement for ground beam of operation house
– Waterproof treatment for the tank area


WAREHOUSE
– Installation of reinforcement, pouring concrete for foundation
– Making wall by corrugated iron for warehouse


BOILER HOUSE
– Maintenance of concrete on the boiler house floor.
– Building the wall; pouring wall bracing
– Making wall by corrugated iron for boiler house

ME SYSTEM
– Installation of rainwater drainage pipes outside the house.
– Installation of cabinets, wind surface, light alignment of dormitory
– Connect wire for street lights
– Installation of highbay lights, sockets, construction of steam pipes, installation of wc equipment, equipment in office are of the raw material factory
– Installing supply pipe outside, installing light power cable.

PCCC/ FIRE PROTECTION
– Connection of main pipes, branch pipes, nozzles, fir detectors, finished product warehouses, raw material factory, textile factory
– Installing the pump for house pump of fire protection tank, fabricating pipe.

Illustrating pictures:

Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 22, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 22, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 22, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 22, 2019