Update Construction Progress Of Xindadong Textiles – Dung Quat On Jan 07, 2020

construction progress of Xindadong Textiles – Dung Quat on Jan 07, 2020
⦁ TEXTILE FACTORY

⦁ • Cleaning and membrane waterproofing axis 12-19 / A-B;
• Construction of ramp, flash curb, sweeping seno for waterproofing, grinding air conditioning room
• Patching air conditioning room
• Clean up garbage outside the factory, avoid waterproofing for wind ditch
 PREPARATION FACTORY FOR RAW MATERIAL
⦁ • building and plastering wall axis 20-25 / C-G
• Installing scaffolding axis C-F / 20
• Air-conditioning room waterproofing
• Putty axis F-H / 20-25
• Tiling brick for foundation A-B / 9-11 axis
• Install fireproof doors
⦁ WASTEWATER TREATMENT AREA – WATER TANK

⦁ • pump Sika for waterproofing tank No. 1
• Installation of formwork of longitudinal beam generates from sedimentation tanks
• Putty matis in house axist 3-4, Paint in axis 1-2, 5-6 operation house
• Installation of door frames of operation house
• Tiling ceramic in the monitoring tank
• Installation of formwork for wall bracing of fire protection houses
• Welding to complete handrail of iron stairs tank no.7, 4
⦁ WAREHOUSE

⦁ Building and plastering walls on the first floor
• Installation of elevator to lift goods
⦁  BOILER HOUSE

⦁ • Plastering edge of the door of boiler house
• Land leveling and repairing, pouring concrete for ground beam lining
• Installation of reinforcement, combine formwork for ground beam
• Ground leveling, concrete pouring for lining of water tank
⦁  GUARD’S HOUSE
⦁ • Fabrication and installation of aluminum frame system
⦁ ME SYSTEM

⦁ • install wire and install street lights
• Installation of textile factory lamps.
• Put the waiting pipe, install boiler house’s cable. Installing trough, hanging lamps for finished product warehouse
• Align equipment for dormitory
• Install exit lights, fault lights, wc exhaust fan. Construction of steam pipes, water supply pipes, install light power cables, light electric plugs, central cabinets, source cabinets of raw material factory
• Install camera, install light power cable outside the house
⦁ FIRE PROTECTION

⦁ • Installation of nozzles, fire detectors for raw material factory, textile factory
• Pressure test of pipe line of raw material factory, textile factory.
• Installation of valves, machine for pump room

 Illustrating pictures:

Update Construction Progress Of Xindadong Textiles – Dung Quat On Jan 07, 2020
Update Construction Progress Of Xindadong Textiles – Dung Quat On Jan 07, 2020
Update Construction Progress Of Xindadong Textiles – Dung Quat On Jan 07, 2020
Update Construction Progress Of Xindadong Textiles – Dung Quat On Jan 07, 2020