Update Construction Progress Of Xindadong Textiles Vietnam On Sep 03, 2019
TEXTILE FACTORY
Building wall axis 22-23 / A-H, 17-21 / A-B
Installation of reinforcement beam cos + 6.90m
Removing reinforcement of the floor beam on the 2nd floor, axis 12-17 / A-B
PREPARATION FACTORY FOR RAW MATERIAL
Installation of formwork, reinforcement, pour concrete for floor beam A-B / 16-25 axis
Suck water in machine base
Installation of reinforcement, formwork for column of 2nd floor of air conditioning room
Building wall covering 2nd floor, A-B axis / 1-9-9
KHU XỬ LÝ NƯỚC THẢI/ WASTEWATER TREATMENT AREA
Tank No. 1: fabrication and installation of reinforcement and formwork of floor beam
Tank No. 2: fabrication and installation of reinforcement and formwork of column
Tank No. 3: fabrication and installation of reinforcement and formwork of pedestrian corridor, hanging wall
Tank No. 5: Fabrication and erection of formwork for pedestrian corridor Tank No. 4: removing formwork for concrete maintenance for pedestrian corridor
INFRASTRUCTURE OUTDOOR
Installation of reinforcement and formwork of bottom, pour concrete for ditch bottom, section M5,6
DORMITORY
Building wall, axis 1-6, 1st floor
Fabrication and installation of reinforcement, formwork for stairs, 1st floor
WAREHOUSE
– pause
GUARD’S HOUSE
– pause
BOILER HOUSE
– pause
FIRE FIGHTING PUMP ROOM, WATER TANK
-pause
ME SYSTEM
– pause