Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 31, 2019

10/10/2020 16:12
Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 31, 2019

The content of construction works is done in past week, Xindadong project

TEXTILE FACTORY

– Cleaning, membrane waterproofing , axis 12-21 / A-B
– Repair door, axis 12-13 / A; H;
– Defect wind ditch, creating a slope of the spray side for air conditioning room no.3
– Building and repair of wing of wind ditch, axis 17-22 / B-D
– Construction of fire protection partition
– Waterproofing and cleaning wind ditches, cleaning on the roof

PREPARATION FACTORY FOR RAW MATERIAL

– Building and plastering axis H-F / 20-25
– Installation of scaffolding axis K-G / 20-21. Remove scaffolding axis J / 14-20
– Putty office area axis A-B / 1-4, K-F / 20-21, Putty axis G / 1-4, A-F / 20-25,
air conditioning room
– Construction of plaster wall axis 20-21 / K-C
– Installing the door for the office area
– Construction of ditches from office area, axis A-B

WASTEWATER TREATMENT AREA – WATER TANK

– Treatment of waterproofing for tank
– Clean up materials for mud sedimentation tank
– Pour concrete for foundation of operation house
– Installation of formwork into monitoring tank
– Construction of wall, axis A, the fire protection house

WAREHOUSE

– Building and plastering walls on the first floor
– 
Making wall by corrugated iron, installing slits of the cross piece on window curtain, roofing balabes

GUARD’S HOUSE

– Putty guard’s house no. 1,2

BOILER HOUSE

– Fabricating steel for water tank
– Installation of reinforcement, combine formwork for foundation of coal warehouse
– Building and plastering wall of boiler house

ME/ ME SYSTEM

– Installation of highbay lights, sockets, installation of cabinets, exit lights, wc equipment, construction of steam pipes, water supply pipe for the factory, installing light electrical cable, the central cabinet of the material factory office area.
– Installation of cameras for textile factory
– Installation of electricity, light electricity for guard’s house
– Align lights, equipment, installing network cable for dormitory
– Installing wires, installing street lights.
– Installing the source for electrical cabinet, raw material factory

TEXTILE FACTORY

– Cleaning membrane waterproofing, axis 12-21 / A-B
– Repair door, axis 12-13 / A; H;
– Defect the wind ditch, creating a slope of the spray for air conditioning room no.3
– Construction and repair of wing of wind ditch, axis17-22 / B-D
– Construction of fire protection partition
– Waterproofing and cleaning of wind ditches, cleaning on the roof

PREPARATION FACTORY FOR RAW MATERIAL

– Building and plastering axis H-F / 20-25
– Installation of scaffolding axis K-G / 20-21. Remove scaffolding axis J / 14-20
– Putty office area axis A-B / 1-4, K-F / 20-21, Putty axis G / 1-4, A-F / 20-25,
air conditioning room
– Construction of plaster wall axis 20-21 / K-C
– Installing the door for the office area
– Construction of ditches from office area, axis A-B

WASTEWATER TREATMENT AREA – WATER TANK

– Treatment of waterproofing for tank
– Clean up materials for mud sedimentation tank
– Pour concrete for foundation of operation house
– Installation of formwork into monitoring tank
– Construction of wall, axis A, the fire protection house

WAREHOUSE

– Building and plastering walls on the first floor
– 
Making wall by corrugated iron, installing slits of the cross piece on window curtain, roofing balabes

GUARD HOUSE

– Putty guard’s house no. 1,2

HOLDER HOUSE

– Fabricating steel for water tank
– Installation of reinforcement, combine formwork for foundation of coal warehouse
– Building and plastering wall of boiler house

ME/ ME SYSTEM

– Installation of highbay lights, sockets, installation of cabinets, exit lights, wc equipment, construction of steam pipes, water supply pipe for the factory, installing light electrical cable, the central cabinet of the material factory office area.
– Installation of cameras for textile factory
– Installation of electricity, light electricity for guard’s house
– Align lights, equipment, installing network cable for dormitory
– Installing wires, installing street lights.
– Installing the source for electrical cabinet, raw material factory

Pictures of construction

Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 31, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 31, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 31, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Dec 31, 2019


Related news


Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020

Plastering wall of roof
Defect beam, column for ceiling of 1st, 2nd, 3rd floor

Show more
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 05, 2020

Fabrication and in stallation of formwork for beam bottom, 3rd floor, factory E

Show more
GOLDEN LOTUS Started The Factory Project Of Perennial Cable Vietnam Co., Ltd. – Phase 2

With role as General Contractor, Golden Lotus has carried out the construction 15 days ahead