Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019

12/10/2020 04:23

Content of works has done:

Factory C11-C12

  1. Factory C11-C12: Mounting columns, collar beam, ridge beam (100%)
  2. Factory C11-C12: Pouring concrete for column, the second floor of office area (100%)
  3. Factory C11-C12: Completing of column, collar beam, ridge beam (100%)

    4. Factory C11-C12: Remove scaffolding, board lining of floor, factory C12

Factory B11

  1. Factory B11: Pouring concrete for floor of 2nd floor of office area (100%)
  2. Factory B11: Installation of board lining, reinforcement loor of 2nd floor of office area (100%)
  3. Factory B11: Completed columns, collar beam, ridge beam (100%)

     4. Factory B11: Pouring concrete to wall bracing and linens in the factory area (70%)

Factory B12

  1. Factory B12: Pouring concrete for floor of 2nd floor of the office area (100%)
  2. Factory B12: Installation of board lining, reinforcement for floor of 2nd floor of the office area (100%)

     3. Factory B12: Pouring concrete to wall bracing and linens in the factory area (85%)

Infrastructure

1.Infrastructure: Excavation of soil, installation of culverts and manholes of factories B11, B12

Pictures of construction

Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019
Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019
Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019
Update Construction Progress Of BW Project – Phase 3 On Sep 22, 2019

GOLDEN LOTUS CONSTRUCTION JSC .,



Related news


Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020

Plastering wall of roof
Defect beam, column for ceiling of 1st, 2nd, 3rd floor

Show more
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 05, 2020

Fabrication and in stallation of formwork for beam bottom, 3rd floor, factory E

Show more
GOLDEN LOTUS Started The Factory Project Of Perennial Cable Vietnam Co., Ltd. – Phase 2

With role as General Contractor, Golden Lotus has carried out the construction 15 days ahead

Show more