Update Construction Progress Of Mahang Project – Dung Quat On Sep 22, 2019

12/10/2020 04:40

Works have done:

Installing reinforcement, formwork for column of wall

Digging foundation, pouring lining, reinforcement, formwork, pouring concrete for foundation of dyeing workshop, completed workshop, waste water treatment tank

Leveling and Compacting land for workshop

Building ditch

Pictures of construction:

Update Construction Progress Of Mahang Project – Dung Quat On Sep 22, 2019
Update Construction Progress Of Mahang Project – Dung Quat On Sep 22, 2019
Update Construction Progress Of Mahang Project – Dung Quat On Sep 22, 2019
Update Construction Progress Of Mahang Project – Dung Quat On Sep 22, 2019

GOLDEN LOTUS CONSTRUCTION JSC .,



Related news


Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020

Plastering wall of roof
Defect beam, column for ceiling of 1st, 2nd, 3rd floor

Show more
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 05, 2020

Fabrication and in stallation of formwork for beam bottom, 3rd floor, factory E

Show more
GOLDEN LOTUS Started The Factory Project Of Perennial Cable Vietnam Co., Ltd. – Phase 2

With role as General Contractor, Golden Lotus has carried out the construction 15 days ahead

Show more