Update Construction Progress Of Vietnam Best Pacific – Phase 2 On Nov 19, 2018

13/10/2020 07:51
Update Construction Progress Of Vietnam Best Pacific – Phase 2 On Nov 19, 2018

Update construction works of Vietnam Best Pacific – Phase 2 on Nov 19, 2018 last week

Main Works of Construction Last Week

BUILDING HOUSE

  1. Combining pipe rack beam
  2. Building and plastering walls
  3. Putty walls
Update Construction Progress Of Vietnam Best Pacific – Phase 2 On Nov 19, 2018
Update Construction Progress Of Vietnam Best Pacific – Phase 2 On Nov 19, 2018


Related news


Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020

Plastering wall of roof
Defect beam, column for ceiling of 1st, 2nd, 3rd floor

Show more
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 05, 2020

Fabrication and in stallation of formwork for beam bottom, 3rd floor, factory E

Show more
GOLDEN LOTUS Started The Factory Project Of Perennial Cable Vietnam Co., Ltd. – Phase 2

With role as General Contractor, Golden Lotus has carried out the construction 15 days ahead