Update construction progress of Perennial Cable project at phase 2B on September 16, 2020
sharpening floor of floor 2 and 3 of factory E
Patching in factory E,F
Rolling and tiling the pavement
chiseling concrete of gate
Compacting Street A4, footing excavation for fence
welding concrete slab cover, dredging ditch and covering concrete slab cover
Clean and complete factory E, F
Complete electrical system of factory F, complete external lighting system
Building fire alarm outside, fabricating bearing frame of Ball fire protection