Update Construction Progress Of Xindadong Textiles Project – Dung Quat On 31/12/2019

Update the construction work of Xindadong project last week TEXTILE FACTORY
– Cleaning, waterproofing 12-21/A-B axis
– Fix the door 12-13/A-H axis
– Defect wind slot, create a slope of the spray surface of the No. 3 control room
– Construction and repair of wind slot 17-22/B-D axis
– Construction of fireproof partitions
– Waterproofing and cleaning wind slot of ditches, cleaning roofs MATERIAL PREPARATION FACTORY
– Build and paint H-F/20-25 axis
– Install scaffolding K-G/20-21 axis, remove scaffolding J/14-20 axis
– Brush putty the office area A-B/1-4, K-F/20-21 axis and G/1-4, A-F/20-25 axis, control room
– Construction drywall 20-21/K-C axis
– Install office door
– Construction ditches in office area A-B axis WASTEWATER TREATMENT AREA
– Waterproofing treatment
– Clean sludge settling tank materials
– Pouring concrete the operator floor
– Install formwork into the monitoring tank
– Build wall of the house for fire protection WAREHOUSE
– Build and paint the 1st floor wall
– Corrugated iron, install door frills, roofing balabes GUARD HOUSE
– Brush putty the guard house BOILER HOUSE
– Process steel of the tank
– Install reinforcement, join formwork for coal warehouse foundation
– Build and paint wall ME/ ME SYSTEM
– Install highbay lights, sockets, install cabinets, place exit lights, WC equipment, construction steam pipes, water pipes for workshop, pull light electric cable, central cabinet in the material workshop office area.
– Install a textile factory camera
– Install electrical, light electricity of the guard house
– Align lights, equipment, pull dormitory network cable
– Pull wire, install street light
– Pull power to electrical cabinet of material preparation factory
Pictures of construction




GOLDEN LOTUS CONSTRUCTION JSC .,