Update Construction Progress Of Xindadong Textiles Project – Dung Quat On 31/12/2019

Cập nhật tiến độ công trình Xindadong Textiles – Dung Quất ngày 31/12/2019

Update the construction work of Xindadong project last week TEXTILE FACTORY

– Cleaning, waterproofing 12-21/A-B axis

– Fix the door 12-13/A-H axis

– Defect wind slot, create a slope of the spray surface of the No. 3 control room

– Construction and repair of wind slot 17-22/B-D axis

– Construction of fireproof partitions

– Waterproofing and cleaning wind slot of ditches, cleaning roofs MATERIAL PREPARATION FACTORY

– Build and paint H-F/20-25 axis

– Install scaffolding K-G/20-21 axis, remove scaffolding J/14-20 axis

– Brush putty the office area A-B/1-4, K-F/20-21 axis and G/1-4, A-F/20-25 axis, control room

– Construction drywall 20-21/K-C axis

– Install office door

– Construction ditches in office area A-B axis WASTEWATER TREATMENT AREA

– Waterproofing treatment

– Clean sludge settling tank materials

– Pouring concrete the operator floor

– Install formwork into the monitoring tank

– Build wall of the house for fire protection WAREHOUSE

– Build and paint the 1st floor wall

– Corrugated iron, install door frills, roofing balabes GUARD HOUSE

– Brush putty the guard house BOILER HOUSE

– Process steel of the tank

– Install reinforcement, join formwork for coal warehouse foundation

– Build and paint wall ME/ ME SYSTEM

– Install highbay lights, sockets, install cabinets, place exit lights, WC equipment, construction steam pipes, water pipes for workshop, pull light electric cable, central cabinet in the material workshop office area.

– Install a textile factory camera

– Install electrical, light electricity of the guard house

– Align lights, equipment, pull dormitory network cable

– Pull wire, install street light

– Pull power to electrical cabinet of material preparation factory

Pictures of construction

Cập nhật tiến độ công trình Xindadong Textiles – Dung Quất ngày 31/12/2019
Cập nhật tiến độ công trình Xindadong Textiles – Dung Quất ngày 31/12/2019
Cập nhật tiến độ công trình Xindadong Textiles – Dung Quất ngày 31/12/2019
Cập nhật tiến độ công trình Xindadong Textiles – Dung Quất ngày 31/12/2019

GOLDEN LOTUS CONSTRUCTION JSC .,