Update Construction Progress Of Mahang Project – Dung Quat On Oct 04, 2019

Update Construction Progress Of Mahang Project – Dung Quat On Oct 04, 2019

Construction work of Mahang project in last week

  1. Construction work of Mahang project in last week
  2. Construction of digging foundation, pouring to lining, reinforcement, formwork, pour concrete for dyeing workshop, completed workshops
  3. Leveling, compact workshop.
  4. Construction of ditches.

Pictures of construction