Update Construction Progress Of Xindadong Textiles – Dung Quat On November 24, 2019

Progress of construction  

TEXTILE FACTORY

– Tiling inside factories, tiling toilets
– Installing septic tanks, combine formwork for fan
– Construction of ground for factory foundation
– Putty outside axis G-H
– Putty outdoor, axis 12-21 / A-B
– Completion of corrugated iron roofing, corrugated iron for wall

PREPARATION FACTORY FOR RAW MATERIAL

– compaction of land for foundation, axis A-B /16-25
– Installation of reinforcement, formwork for warter drainage ditch
– Welding steel V ditches in the house
– Concrete maintenance for factory foundation
– Installation of reinforcement  for septic tank, axis A
– Paint color outside, axis A-B/25; A /17-25; putty in house, 2nd floor
– Building and plastering wall, axis K-M / 5-11; building and plastering wall around warehouse
– Tiling wall for toilet on the 1st floor
– Test waterproof for toilets, office area
– 
Making wall by corrugated iron, seamlock tole, completion for roof
– Putty in house, axis J + 7000-K / 1-8
– Making handrail by inox

INFRASTRUCTURE OUTDOOR

Combine formwork, pour concrete for Road D5

Leveling road from wastewater treatment bank

– Painting seno for roof of attic
– Cleaning corner, sweeping WC, 4th floor, axis 1-10
– Building to prvent water splash, 4th floor
– Paint 1st layer outside, axis 1. Paint to finish layer 2. Paint 2nd layer outside, D axis
– Putty, install to finish the outside of the 3rd floor, axis A
– Construction of installing door for 4th floor

WASTEWATER TREATMENT AREA

Tank no.2: remove formwork, tidy up materials

WAREHOUSE

Spead deck floor, installation of purlins, roofing corrugated iron

GUARD’S HOUSE

Tiling guard’s house

ME/ ME SYSTEM

– Aligning, testing of compressed air pressure, construction of light electric cable troughs for textile factory.
– Construction, aligning of steam pipe rack, installing light. Installing socket wire for lighting, Exit lights, supply source of installation of lighting cabinets for raw materials factory.
– Installation of plugs, telephone cables, lights in dormitory
– Hanging cables, hang lights for textile factory
– Installing street lights, put rainwater drainage pipes

– Installation of pipes for fire fighting, painting fireproof for material factory
– Installing thread rod, Installation of fire fighting pipes for textile factory 

– Fabricating pipes.

Picture of construction: 

Update Construction Progress Of Xindadong Textiles – Dung Quat On November 24, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On November 24, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On November 24, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On November 24, 2019