Update Construction Progress Of Xindadong Textiles Project – Dung Quat On March 12, 2020
construction progress of Xindadong
TEXTILE FACTORY
Patching air-conditioning no. 4
Waterproofing, cutting thread rod of wind ditches
Clean the factory floor
Patching, plastering axis 23
PREPARATION FACTORY FOR RAW MATERIAL
Shrinking of floor, K-M axis / 1-11
Patching, plastering wall, K-M axis/ 14-20, F-H axis/ 20-25
Plastering wall, rotating electrical cabinets
INFRASTRUCTURE OUTDOOR
Ground leveling
Defect ditch, defect road, manhole
Build a garbage house
WASTEWATER TREATMENT AREA
Plastering wall outside, inside, tank number 2
Painting outside wall, tank number 7
Crane, spread foam, steel mesh welded on pump roof
WAREHOUSE
Patching and cleaning floor of warehouse
Construction of fireproof walls
ME SYSTEM
Aligning lights outside
Cleaning materials yard.
Aligning and cleaning inox sheet of air pipe.
Repair electrical system of IT room.
FIRE PROTECTION
Test pressure, test pipes outside
Pictures of construction: