Update Construction Progress Of Perennial Cable Project – Phase 3 On May 29, 2020

Progress:

– Fabrication of iron and steel formwork for floor beam of roof X1-8 / Y1-5 axis, factory E
– Dismantle formwork of floor beam of 3rd floor, factory E
– Installing net covering outside, arranging materials of factory E
– Building wall, fabrication of formwork for pillars, X1-X8/Y5 axis, factory E
– Installing formwork for floor of 2nd floor of toilet area of factory F
– Plastering wall of factory F, auxiliary house
– Combine formwork to pour concrete for ditch wall A4-A4.1
–  Digging soil, pouring concrete to line ditch route A7-A9
–  Installing recessed pipes for push buttons, fire alarms T1, factory E
–  Installing recessed pipes for switches, sockets T1, factory E

Update Construction Progress Of Perennial Cable Project – Phase 3 On May 29, 2020
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 29, 2020
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 29, 2020
Update Construction Progress Of Perennial Cable Project – Phase 3 On May 29, 2020