Update construction progress of Mahang project on September 17, 2020

  1. FACTORY HAS BEEN COMPLETED
    –  Building machine base C-D
    –  Prepare to pour concrete for M-J axis / 9-16
    –  Building tiling of the second floor of laboratory.
    2. DYEING FACTORY
    –  Continue to complete steel, pipe elevation, chisels at junction of 3-9 / H-J axis–  Maintenance of concrete on 3-9 / J-K axis
    3. INFRASTRUCTURE :
    –  Building signs.
    –  Building weighbridge, side gate.
    –  Building pavement of dyeing workshop.
    –  Implementing road maintenance 4.4, C1.
    4. FIRE PROTECTION TANK, WAREHOUSE OF COALS, GUARD’S HOUSE, BOILER HOUSE
    –  Fabricating reinforcement for the floor of boiler house–  installing of steel V for ditch of boiler house
    –  Laying stone to mix the floor of boiler house and compact it
    5. ME System
    –  Building fire fighting system of the first floor for the completed workshop.
    –  Installing  pump room for fire fighting

Pictures of construction

Update construction progress of Mahang project on September 17, 2020
Update construction progress of Mahang project on September 17, 2020
Update construction progress of Mahang project on September 17, 2020