Update construction progress of Mahang project on September 17, 2020
- FACTORY HAS BEEN COMPLETED
– Building machine base C-D
– Prepare to pour concrete for M-J axis / 9-16
– Building tiling of the second floor of laboratory.
2. DYEING FACTORY
– Continue to complete steel, pipe elevation, chisels at junction of 3-9 / H-J axis– Maintenance of concrete on 3-9 / J-K axis
3. INFRASTRUCTURE :
– Building signs.
– Building weighbridge, side gate.
– Building pavement of dyeing workshop.
– Implementing road maintenance 4.4, C1.
4. FIRE PROTECTION TANK, WAREHOUSE OF COALS, GUARD’S HOUSE, BOILER HOUSE
– Fabricating reinforcement for the floor of boiler house– installing of steel V for ditch of boiler house
– Laying stone to mix the floor of boiler house and compact it
5. ME System
– Building fire fighting system of the first floor for the completed workshop.
– Installing pump room for fire fighting