Update Construction Progress Of Perennial Cable Project Phase 2B On Aug 05, 2020

 Contents of construction work during week:

–  Removal of outer scaffolding of the X8 / Y1-Y5, axis, workshop E–  Installing iron and steel for foundation of floor 1 of workshop E
–  Paint color in the house on the 3rd floor, X7-8 / Y1-2 axis, putty outside the house X1-8 / Y5  axis, workshop E
–  Installing reinforcement for foundation of workshop F
–  Pour concrete for foundation of workshop F
–  Building additional wall for workshop F