Update Construction Progress Of Mahang Project On Jun 19, 2020
- RESEARCH AND DEVELOPMENT HOUSE
– Defect, putty stairs
– Installing glass for hand-rail of terrace of the 3rd floor - COMPLETED FACTORY
– Defect floor of 3rd floor
– Building walls of laboratory of 2nd floor
– Putty walls of roof
– Installing of Aluminum Frame for Toilet - DYEING FACTORY
– Fabrication and installation of formwork for staircase of room.
– Installing formwork for partition of room
– Installing formwork, reinforcement for floor of ditch cover, J-K axis
– Preparing to pour concrete for ditch cover
– Building and plastering 2nd floor for room cos +1.87m
– Fasten settlement joint for ground floor
4. INFRASTRUCTURE :
– Installing ballasting foundation of section B3
– Installation for rainwater
– Installing flash curb
5. FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE
– Installing formwork, reinforcement for ditch of coal warehouse– Installing window for guard’s house.
6. ME System
– Installing fire fighting pipes for 1st floor of completed factory– Test tube routes outside house.
– Building manholes outside
– Connecting water supply, repairing water drainage pipe for dyeing factory– Installation of air conditioners for first floor of the R&D House