Update Construction Progress Of Mahang Project On Jun 19, 2020

  1. RESEARCH AND DEVELOPMENT HOUSE
    –  Defect, putty stairs
    –  Installing glass for hand-rail of terrace of the 3rd floor
  2. COMPLETED FACTORY
    –  Defect floor of 3rd floor
    –  Building walls of laboratory of 2nd floor
    –  Putty walls of roof
    –  Installing of Aluminum Frame for Toilet
  3. DYEING FACTORY

–  Fabrication and installation of formwork for staircase of room.
–  Installing formwork for partition of room
–  Installing formwork, reinforcement for floor of ditch cover, J-K axis
–  Preparing to pour concrete for ditch cover
–  Building and plastering 2nd floor for room cos +1.87m
–  Fasten settlement joint for ground floor

4. INFRASTRUCTURE :
–  Installing ballasting foundation of section B3
–  Installation for rainwater
–  Installing flash curb

5. FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE 
–  Installing formwork, reinforcement for ditch of coal warehouse–  Installing window for guard’s house.

6. ME System
–  Installing fire fighting pipes for 1st floor of completed factory–  Test tube routes outside house. 
–  Building manholes outside 
–  Connecting water supply, repairing water drainage pipe for  dyeing factory–  Installation of air conditioners for first floor of the R&D House

Illustrating pictures

Update Construction Progress Of Mahang Project On Jun 19, 2020
Update Construction Progress Of Mahang Project On Jun 19, 2020
Update Construction Progress Of Mahang Project On Jun 19, 2020
Update Construction Progress Of Mahang Project On Jun 19, 2020