Update Construction Progress Of Perennial Cable Project – Phase 3 On Apr 6, 2020
Main works is done in day
– Fabrication, installation of reinforcement, formwork for foundation, X3-4/Y3 axis, pour concrete for Ground beam, X7- 8/Y1-5 axis, factory E
– Compacting soil to septic tank lining, factory E
– Fabrication of reinforcement, formwork for pedestal, factory F
– dismantling formwork for maintenance of foundation concrete of factory F
– Pour concrete for ground beam of house E: 50%