Update construction progress of Best Pacific Vietnam Project – Phase 2 on Jun 05, 2019
Contents of construction work:
- Completing electromechanical ditches, hot water tanks
- Complete lights for 1st, 2nd, 3rd floor
- Installing cables
- Connect the pneumatic hose
- Installing chiller system
- Installing wind pipe for 1st, 3rd floor
- Fire fighting: installing fire fight water hose for 1st, 2nd, 3rd floor
- Painting plaster wall of 3rd floor
- screwing for ceiling of 3rd floor
- Painting fireproof wall
- Clean factory
- Digging land for tank D4