Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On June 20, 2019

CONSTRUCTION OF HOUSE

  1. Pour concrete lining the machine base generated outside the house;
  2. Completion of light for 1st, 2nd, 3rd floor;
  3. Installation of Power supply cable;
  4. Construction of steam pipes, condensate pipes on the first floor;
  5. Fire protection: pressure test for 3rd floor, installation of fire fighting system for 1st, 3rd floor;
  6. Painting plaster wall for 3rd floor;
  7. Painting to complete wall indoor and outdoor;
  8. Sanitation of factory;
  9. Installation of steel for base of tank D4;
  10. Installation of formwork for tank D4;
  11. Installation of waterbar for tank wall D4;

pictures of construction

Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On June 20, 2019
Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On June 20, 2019
Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On June 20, 2019
Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On June 20, 2019