Update Construction Progress Of Best Pacific Vietnam Project – Phase 2 On June 20, 2019
CONSTRUCTION OF HOUSE
- Pour concrete lining the machine base generated outside the house;
- Completion of light for 1st, 2nd, 3rd floor;
- Installation of Power supply cable;
- Construction of steam pipes, condensate pipes on the first floor;
- Fire protection: pressure test for 3rd floor, installation of fire fighting system for 1st, 3rd floor;
- Painting plaster wall for 3rd floor;
- Painting to complete wall indoor and outdoor;
- Sanitation of factory;
- Installation of steel for base of tank D4;
- Installation of formwork for tank D4;
- Installation of waterbar for tank wall D4;