Update Construction Progress Of BW Project – Phase 3 On Jul 19, 2019

Contents of construction work:

Factory C11,C12

  1. Factories C11-C12: Installation of board lining,reinforcement, H axis and pouring concrete for foundation, H axis

     2. Factories C11-C12: Digging foundation of A axis and pouring concrete to lining A axis

Factory B11

1. Factory B11: Digging foundation for axis 13 and pouring concrete to lining axis 13

Factory B12

  1. Factory B12: Installation of board lining, reinforcement, A axis and pouring concrete A axis

2. Factory B12: Continue to dig foundation and pour concrete to lining, B axis

Factory C4

1. Factory C4: Remove board lining of pedestal, axis A and clean the foundation

Factory C5

  1. Factory C5: Continuing to dig foundation, A axis and pouring concrete to lining, A axis

     2. Factory C5: Fabricating foundation steel

Temperary electrical phase 3

  1. Continue to build temporary power lines

     2. Digging soil, transportation of ground soil C5, C11

Illustrating pictures:

Update Construction Progress Of BW Project – Phase 3 On Jul 19, 2019
Update Construction Progress Of BW Project – Phase 3 On Jul 19, 2019
Update Construction Progress Of BW Project – Phase 3 On Jul 19, 2019
Update Construction Progress Of BW Project – Phase 3 On Jul 19, 2019