Update Construction Progress Of BW Project – Phase 3 On Jul 19, 2019
Contents of construction work:
Factory C11,C12
- Factories C11-C12: Installation of board lining,reinforcement, H axis and pouring concrete for foundation, H axis
2. Factories C11-C12: Digging foundation of A axis and pouring concrete to lining A axis
Factory B11
1. Factory B11: Digging foundation for axis 13 and pouring concrete to lining axis 13
Factory B12
- Factory B12: Installation of board lining, reinforcement, A axis and pouring concrete A axis
2. Factory B12: Continue to dig foundation and pour concrete to lining, B axis
Factory C4
1. Factory C4: Remove board lining of pedestal, axis A and clean the foundation
Factory C5
- Factory C5: Continuing to dig foundation, A axis and pouring concrete to lining, A axis
2. Factory C5: Fabricating foundation steel
Temperary electrical phase 3
- Continue to build temporary power lines
2. Digging soil, transportation of ground soil C5, C11