Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020

The progress of mahang project until April 14, 2020
- RESEARCH AND DEVELOPMENT HOUSE
– Installing door frame of 4th floor - COMPLETED WORKSHOP
– Plastering wall of roof
– Defect beam, column for ceiling of 1st, 2nd, 3rd floor
– Installing steel for wall of ditch phase 02, 9a-16/L-K axis
– Installing steel for floor of ditch, 9a-16/K-J axis - DYEING WORKSHOP
– Building and plastering to stop membrane of roof
– Dado wall of toilet of ground floor
– Defect walls of 2nd floor
– Installing glass door of ground floor - INFRASTRUCTURE
- FIRE FIGHTING TANK, COAL WAREHOUSE
- ME System
– Chiseling, put cabinets, installing cable of 4th floor, installing light wire when having trouble– Chiseling 2nd floor, 3rd floor of dyeing workshop, completed workshop.
– Installing hdpe pipe lighting system through the main gate.– Complete drainage pipe of completed workshop