Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020

Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020

The progress of mahang project until April 14, 2020

  1. RESEARCH AND DEVELOPMENT HOUSE
    – Installing door frame of 4th floor
  2. COMPLETED WORKSHOP
    – Plastering wall of roof
    – Defect beam, column for ceiling of 1st, 2nd, 3rd floor
    – Installing steel for wall of ditch phase 02, 9a-16/L-K axis
    – Installing steel for floor of ditch, 9a-16/K-J axis
  3. DYEING WORKSHOP
    – Building and plastering to stop membrane of roof
    – Dado wall of toilet of ground floor
    – Defect walls of 2nd floor
    – Installing glass door of ground floor
  4. INFRASTRUCTURE
  5.  FIRE FIGHTING TANK, COAL WAREHOUSE 
  6. ME System
    – Chiseling, put cabinets, installing cable of 4th floor, installing light wire when having trouble– Chiseling 2nd floor, 3rd floor of dyeing workshop, completed workshop.
    – Installing hdpe pipe lighting system through the main gate.– Complete drainage pipe of completed workshop

Pictures of construction

Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020
Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020
Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020
Update Construction Progress Of Mahang Project – Dung Quat On Apr 14, 2020