Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020

RESEARCH AND DEVELOPMENT

– Fabricating and installing septic tank, axis 1-2
– Fabricating and installing stairs, axis 8-9, 4th floors to roof.
– Paving 2nd floor, tiling 3rd floor, 4th floor.
– Exterior plastering of wall for C / 3-4.9-10 axis. Putty outside.
– Installation of door frame on 2nd floor, Roof waterproofing.


2. COMPLETED FACTORY
– Fabrication and installation of steel for floor beam 2.9, 1-2 axis / D-H
– Plastering ceiling on 2nd floor, outer surface of M-J axis.
– Building walls, the 3rd floor, H axis / 9-17, plastering the third floor outside, the A-H / 16 axis.
– Grinding ceilings and plastering pillars on the 3rd floor.
– Roof waterproofing.
– Installation of steel for floor, axis 2-9 / M-L, axis 2-9 / K-J.
– Prepare to pour concrete for wall phase 2 axis 9a-16 / K-J.

3. DYEING FACTORY
– Chống thấm mái thi công màng kho.
– Construction of wall, the 3rd floor, room AC.
– Continue to grind ceiling columns, plaster on the 1st and 2nd floor, 3rd floor.
– Fabrication and installation of floor beam cote 6.1, girder bridge No. 3.
– Dismantle stair axis 11-12 from cote 6.2-14.6.
– Roof waterproofing, construction of warehouse membranes.


4. INFRASTRUCTURE

– Construction of temporary drainage, temporary roads.
– Construction of ditch A10-A11, A11-A18, A09-A10.
– Construction of wastewater from NT3-01 to NT3-05 section.
– Compacting CP for streets DA5, D2.4.

5. FIRE PROTECTION TANK, COAL WAREHOUSE
– Fabrication and installation of formwork for pump room
– Fabrication and installation of formwork for ground beam of the warehouse.
– Clean the fire protection tank.

6. WASTE WATER TANK S08A
– Installation of reinforcement, formwork for wall of ditch cos +4000.


7. ME SYSTEM

– Construction of water supply to WC, Chiseling, putting pipe for dyeing factory, completed factory, R&D house
– Construction of fire extinguishing system for R&D house, dyeing workshop, completed factory.
– Construction of WC water supply and drainage pipes to completed factory.


Pictures of construction of Mahang:

Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020
Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020
Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020
Update Construction Progress Of Mahang Project – Dung Quat On March 12, 2020