Update Construction Progress Of Mahang Project – Dung Quat On Sep 22, 2019

Works have done:

Installing reinforcement, formwork for column of wall

Digging foundation, pouring lining, reinforcement, formwork, pouring concrete for foundation of dyeing workshop, completed workshop, waste water treatment tank

Leveling and Compacting land for workshop

Building ditch

Pictures of construction: