Update Construction Progress Of Mahang Project – June 10, 2020

1. RESEARCH AND DEVELOPMENT HOUSE
– Putty gypsum ceiling, void square
– Clean glass doors on the 2nd floor.
– Cleaning brick floor of the first floor
2. COMPLETED FACTORY
– Maintenance of concrete on axis 16-17.
– Installation of formwork and rainwater ditch.
– Construction of ramp for axis A, axis 17.
– Completion of stairs of 1-2 axis.
– Construction of the laboratory wall on the 2nd floor.
– Installation of aluminum and glass door frames on the 2nd floor.
3. DYEING FACTORY
– Dismantling formwork of floor beam cos + 1.78m.
– Dismantling formwork of beam cos 4.59m air conditioning room
– Installing formwork, reinforcement for ditch, G-H axis
– Dismantling formwork of wall of ditch phase 2, J-K axis
– Welding ditch of rainwater.
– Installing glass door frames
– Fasten settlement joint of ground floor
– Installing handrail of stairs of axis 1-2
4. INFRASTRUCTURE :
– Installing flash curb
– Installing wastewater manholes, electric manholes
– Building cement concrete for street section B1,2.3,2.4
5. FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE :
– Building chamfer angle, clarifier, fire fighting tank
– Putty, spotting in rubbish house, guard’s house
6. ME/ ME System:
– Installing lighting system outside
– Installing fire fighting t1, t3 of dyeing factory.
– backfilling land for outdoor fire fighting pillars, Fabricating pipes.
– Installing outside, fixing error t2, t3 R&D house
– Connect clean water to the R&D house.