Update Construction Progress Of Mahang Project – June 10, 2020

Update Construction Progress Of Mahang Project – June 10, 2020

1.   RESEARCH AND DEVELOPMENT HOUSE
–   Putty gypsum ceiling, void square  
–   Clean glass doors on the 2nd floor.
–  Cleaning brick floor of the first floor
2.  COMPLETED FACTORY   
–   Maintenance of concrete on axis 16-17. 
–   Installation of formwork and rainwater ditch. 
–   Construction of ramp for axis A, axis 17. 
–   Completion of stairs of 1-2 axis.
–   Construction of the laboratory wall on the 2nd floor. 
–   Installation of aluminum and glass door frames on the 2nd floor.
3.  DYEING FACTORY
–   Dismantling formwork of floor beam cos + 1.78m.
–   Dismantling formwork of beam cos 4.59m air conditioning room
–   Installing formwork, reinforcement for ditch, G-H axis
–   Dismantling formwork of wall of ditch phase 2, J-K axis
–   Welding ditch of rainwater.
–   Installing glass door frames
–   Fasten settlement joint of ground floor
–   Installing handrail of stairs of axis 1-2
4.   INFRASTRUCTURE :
–  Installing flash curb
–   Installing wastewater manholes, electric manholes
–   Building cement concrete for street section B1,2.3,2.4
5.   FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE  : 
–  Building chamfer angle, clarifier, fire fighting tank
–   Putty, spotting in rubbish house, guard’s house
6.  ME/ ME System:
–   Installing lighting system outside 
–   Installing fire fighting t1, t3 of dyeing factory. 
–   backfilling land for outdoor fire fighting pillars, Fabricating pipes. 
–   Installing outside, fixing error t2, t3 R&D house 
–   Connect clean water to the R&D house.

Pictures of construction:

Update Construction Progress Of Mahang Project – June 10, 2020
Update Construction Progress Of Mahang Project – June 10, 2020
Update Construction Progress Of Mahang Project – June 10, 2020
Update Construction Progress Of Mahang Project – June 10, 2020