Update Construction Progress Of Mahang Project On Aug 24, 2020
Construction diary
- COMPLETED FACTORY
– Implementing wall plastering of 8-9 / H axis
– Rolling and tiling laboratory
– Building the ground of air conditioning ditch areas
– Building machine base of C-D axis / 11-16
– Installing steel for floor of M-J axis/2-9/ - DYEING FACTORY
– Backfilling pipe neck for air conditioning ditch
– Building base machine reinforcing, water tank of cold room– Building defect for floor of 2nd floor
– Plastering wall for air conditioning room - INFRASTRUCTURE
– Building signs.
– Building flush curb, manholes
– Building weighbridge, side gate. - FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE
– Installing machine base formwork and steam trench of machine base 15 tons for boiler house
– Building floor defect for pump room - ME System
– Installing additional protective collar device
– Building and repairing fire protection cabinets of 1st floor for completed factory– Building rain water drainage pipes for coal warehouse, boiler house