Update Construction Progress Of Mahang Project On Aug 24, 2020

Construction diary

  1. COMPLETED FACTORY
    –  Implementing wall plastering of 8-9 / H axis
    –  Rolling and tiling laboratory
    –  Building the ground of air conditioning ditch areas
    –  Building machine base of C-D axis / 11-16
    –  Installing steel for floor of M-J axis/2-9/
  2. DYEING FACTORY
    –  Backfilling pipe neck for air conditioning ditch
    –  Building base machine reinforcing, water tank of cold room–  Building defect for floor of 2nd floor
    –  Plastering wall for air conditioning room
  3.  INFRASTRUCTURE
    –  Building signs.
    –  Building flush curb, manholes
    –  Building weighbridge, side gate.
  4. FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE
    –  Installing machine base formwork and steam trench of machine base 15 tons for boiler house
    –  Building floor defect for pump room
  5.  ME System
    –  Installing additional protective collar device
    –  Building and repairing fire protection cabinets of 1st floor for completed factory–  Building rain water drainage pipes for coal warehouse, boiler house

Pictures of construction

Update Construction Progress Of Mahang Project On Aug 24, 2020
Update Construction Progress Of Mahang Project On Aug 24, 2020
Update Construction Progress Of Mahang Project On Aug 24, 2020
Update Construction Progress Of Mahang Project On Aug 24, 2020