Update Construction Progress Of Mahang Project On Jul 13, 2020

 Progress of Mahang project

  1. COMPLETED FACTORY
    –  Defect for floor of 3rd floor
    –  Putty mastic for ground floor.
    –  Plastering wall for laboratory at 2nd floor
  2.  DYEING FACTORY
    –  Installing formwork, reinforcement at ditch for phase 2, H-J axis
    –  Plastering wall of 2nd floor for room–  Building foundation
  3.  INFRASTRUCTURE
    –  Installing wastewater manholes
    –  Building cement concrete, street section 3.3.
    –  Installing ditch to put pipes across the street
  4.  FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE
    –  Waterproofing chemical treatment tank, fire fighting tank 
    –  Installing reinforcement for foundation of chemical warehouse
  5. ME System
    –  Installing connection of IT room, electromechanical entire testing of RD house..
    –  Installing equipment for protective house
    – Test and edit lighting outside
    – Replace pipe rack on the 2nd floor of the completed factory

Pictures of construction

Update Construction Progress Of Mahang Project On Jul 13, 2020
Update Construction Progress Of Mahang Project On Jul 13, 2020
Update Construction Progress Of Mahang Project On Jul 13, 2020
Update Construction Progress Of Mahang Project On Jul 13, 2020