Update Construction Progress Of Mahang Project On Jul 13, 2020
Progress of Mahang project
- COMPLETED FACTORY
– Defect for floor of 3rd floor
– Putty mastic for ground floor.
– Plastering wall for laboratory at 2nd floor - DYEING FACTORY
– Installing formwork, reinforcement at ditch for phase 2, H-J axis
– Plastering wall of 2nd floor for room– Building foundation - INFRASTRUCTURE
– Installing wastewater manholes
– Building cement concrete, street section 3.3.
– Installing ditch to put pipes across the street - FIRE PROTECTION TANK, WAREHOUSE OF COALS, PROTECTION HOUSE, BOILER HOUSE
– Waterproofing chemical treatment tank, fire fighting tank
– Installing reinforcement for foundation of chemical warehouse - ME System
– Installing connection of IT room, electromechanical entire testing of RD house..
– Installing equipment for protective house
– Test and edit lighting outside
– Replace pipe rack on the 2nd floor of the completed factory