Update Construction Progress Of Perennial Cable Project Phase 3 On Jul 17, 2020
Progress of construction
– Plastering exterior walls, stairs for the third floor, X1-2 / Y5; X5-8 axis, riser, factory F
– Putty house outside, X1/Y1-5 axis, factory F
– Fabricating and installing formwork, reinforcement for ditch in factory F
– Roofing corrugated iron for factory F