Update Construction Progress Of Perennial Cable Project – Phase 3 On May 05, 2020

Works was done on May 5, 2020 Perennial Cable Project – Phase 3
– Fabrication and in stallation of formwork for beam bottom, 3rd floor, factory E
– Installing scaffolding against floor of 3rd floor, X1-8 / Y1-5 axis, factory E
– Pour concrete of underground concrete walls C; D and concrete of pillars, X1-X2 axis, factory F
– Building walls of factory F and auxiliary houses
– Digging ditch route A.1 to A.1.1
Illustrated construction pictures