Update Construction Progress Of Suncasa Project On September 16, 2020

Construction progress:

– Fabricate floor beam, ground beam

– Installing formwork for stairs D-31.27,28

– Installing steel for floor beam D-31.36,37,38

– Moving land, crush land for foundation  

– Compacting land for ground beam D-31.49,50, Compacting land for ground floor D-31.42,43,44,45

– Installing cos+3550 floor for house 36,37,38

– Compacting soil for ground floor of house 42,43,44

– Installing formwork for stairs of house 27,28