Update Construction Progress Of Tating Plastic – phase 2 – 09/10/2019

Last week construction progress of Tating Plastic Project – Phase 2 on Oct 09, 2019

  1. Fabricating steel for foundation framework and foundation beam
  2. Installing board lining for foundation beam
  3. Installing foundation beam
  4. Installing board lining for foundation framework
  5. Installing foundation framework steel
  6. Pouring concrete for foundation framework
  7. Digging land for foundation framework
  8. Installing bolts of column base