Update Construction Progress Of Tating Plastic Project On Jan 06, 2019

Update Construction Progress Of Tating Plastic Project On Jan 06, 2019

Content of main works

Factory 1,2

  1. Brick wall, installation of reinforcement, formwork for column, tie-beam;
  2. Fill stone for ground;

Warehouse

  1. Brick wall, installation of reinforcement, formwork for column, tie-beam;
  2. Fill stone for ground;

Training house

  1. Installation of reinforcement, formwork for slab-beam on 1st floor.

*Canteen building

  1. Installation of reinforcement, formwork for slab-beam on 1st floor.

* House Office

  1. Fabrication, installation of steel, pouring concrete  for ground beam;

Infrastructure

  1. Installation of storm, water drainage manhole;
  2. Levelling ground of road;
  3. Manufacture sheet of mainhole, curb of road;

Fence

  1. Fabrication, installation of steel fence;

Water tank

  1. Installation of  formwork for wall

Pictures of construction

Update Construction Progress Of Tating Plastic Project On Jan 06, 2019
Update Construction Progress Of Tating Plastic Project On Jan 06, 2019
Update Construction Progress Of Tating Plastic Project On Jan 06, 2019