Update Construction Progress Of Tating Plastic Project On Jan 06, 2019

Content of main works
Factory 1,2
- Brick wall, installation of reinforcement, formwork for column, tie-beam;
- Fill stone for ground;
* Warehouse
- Brick wall, installation of reinforcement, formwork for column, tie-beam;
- Fill stone for ground;
* Training house
- Installation of reinforcement, formwork for slab-beam on 1st floor.
*Canteen building
- Installation of reinforcement, formwork for slab-beam on 1st floor.
* House Office
- Fabrication, installation of steel, pouring concrete for ground beam;
* Infrastructure
- Installation of storm, water drainage manhole;
- Levelling ground of road;
- Manufacture sheet of mainhole, curb of road;
* Fence
- Fabrication, installation of steel fence;
* Water tank
- Installation of formwork for wall