Update Construction Progress Of Tating Plastic Project – Phase 2 On Oct 03, 2019

Update Construction Progress Of Tating Plastic Project – Phase 2 On Oct 03, 2019

construction works past week:

Pile joint  26 center points (total 279/316 center point )

Receive pile and take them to construction site

Installing steel for foundation framework

Installing board lining for foundation framework

Digging land for foundation framework

Pouring concrete for foundation framework

Remove formwork for foundation framework

Backfilling foundation framework

Compacting land to level foundation framework

Illustrating pictures of construction:

Update Construction Progress Of Tating Plastic Project – Phase 2 On Oct 03, 2019
Update Construction Progress Of Tating Plastic Project – Phase 2 On Oct 03, 2019
Update Construction Progress Of Tating Plastic Project – Phase 2 On Oct 03, 2019
Update Construction Progress Of Tating Plastic Project – Phase 2 On Oct 03, 2019